Works in hands (09)

Client: As A Sub-Contract Agreement With NEIE China

Project: JICA Loan No. PK-61 NTDC Contract No. CH-001 220/132 KV New Chistian Substation & 220KV Vehari Sub-Station Extension (As A Sub-Contractor with NEIE China)

Work Type: Design, Manufacture,Supply, Installation, Testing & Commissioning of Plant Equipment and Associated Civil Works for 220/132kV Chistian Substation & 220kV Vehari Substation Extension Project.

Percentage of Work Done: 45%

Value Rs. 270 Million

Client: Chief Engineer (EHV-I), NTDC Lahore

Project: Contract No. ADB-58-2010 220 KV Okara Grid Station (As JV with NEIE)

Work Type: Civil Works, Erection, testing & Commissioning

Percentage of Work Done: 89%

Value Rs. 104,849,048

Client: Sub Contract Agreement With NEIE China

Project: JICA Loan PK-61 NTDC Contract No. VC-001 220kV Double Circuit Twin Bundle Transmission Line Vehari-Chistian (As Sub-Contractor with NEIE China)

Work Type: Design, Manufacture, Supply, Installation , Testing & Commissioning of 220kV Double Circuit Twin Bundle Vehari-Chisitan Transmission Line

Percentage of Work Done: 40%

Value Rs. 500 Million

Client: Chief Engineer (EHV-I), NTDC Lahore

Project: 220 KV Kassowal 220 KV AIS Substation Kassowal (As sub-contractor with M/s TBEA Consortium)

Work Type: Supply, Construction , Erection, Testing & Commissioning

Percentage of Work Done: 82%

Value Rs. 14.39 Million

Client: Project Director (GSC) MEPCO Multan

Project: Bidding Document No. MEPCO/WB-STG-51 132kV SDT Vehari-Ludden Transmission Line (As a Main Sole Contractor)

Work Type: For Construction of Tower Foundations, Erection , Stringing, Testing and Commissioning of 132kV SDT Transmission Line

Percentage of Work Done: 80%

Value Rs. 15,547,482.00

Client: Chief Engineer (Development) IESCO, Islamabad

Project: Contract No. IESCO/WB/PMU/TL/NCB-09 Procurement of works for 132KV Transmission lines (NCB-09) Fateh Jang to Pindi Gheb (Feed for Pindi Gheb Grid Station) and In and Out Fateh jang to Pindi Gheb (Feed for Ahmadal Grid Station) Under World Bank Financing (APL-I)(As JV with NEIE)

Work Type: Survey, foundation, erection, testing and commissioning

Percentage of Work Done: 95%

Value Rs. 78,532,443

Client: Sub-Contract Agreement with NEIE

Project: 500kV Shikarpur Grid Station Up-gradation of 220 kV AIS Substation Sikharpur to 500kV Level (As Sub-Contractor with M/s NEIE China)

Work Type: Design , Manufacture ,Supply, Installation, Testing and Commissioning of Plant Equipment and Associated Civil Works for 500kV New Shikarpur Substation

Percentage of Work Done : 20%

Value Rs. 650 Million

Client: MEPCO Chief Engineer (Development) MEPCO Multan.

Project: Contract No. ABB-2727-MEPCO-15 & 16 132kV AIS Grid Station Miran Pur and 132kV New Transmission Line (Lot-2) (As A Joint Venture Partner With NEIE)

Work Type: New AIS Turn Key Substation , Transmission Line and Residential Quarters

Percentage of Work Done 20%

Value Rs. 181,729,741.37 + US$ 1,347,254.00

Client: MEPCO Chief Engineer (Development) MEPCO Multan.

Project: Contract No. ABB-2727-MEPCO-17 & 18 132 KV AIS Noor Sur Grid Station and New Transmission Line (Lot -II) (As JV with NEIE)

Work Type: Conversion of 66 KV AIS Grid Station to 132 KV AIS on Turn Key Basis

Percentage of Work Done 40%

Value Rs. 79,678,941.60 & USD 4,35,107.00